Meeting 4 - Lisbon May 2010The 4th Project meeting was hosted by the Instituto de Orientação Profissional, Universidade de Lisboa during the 4th and 5th of May 2010 in Lisbon.
Please click on the links below to see copies of the meeting documents
| Area | Action point | Responsible | Deadline |
| Video | Draft tender created by Careers Europe and sent to CXL | MC, Careers Europe | Asap |
| Three tenders considered, video producer chosen | JC, DE | Asap | |
| Model storyboard sent by BEST to CXL | HK, BEST | Asap | |
| CXL drafts storyboard in English, at same time partners send to CXL any key messages/ words they wish included in storyboard. | CXL and European partners | ||
| CXL sends draft storyboard to partners. Partners add comments (if necessary) and return to CXL | CXL and European partners | ||
| Final storyboard completed by CXL | CXL | 1st June | |
| Draft video produced | Producer | ||
| Draft video sent via CXL to partners. Partners produce translations for the subtitles required in their final video version. Translations returned to CXL and Producer to add subtitles to final video. | CXL and European partners | ||
| Final versions of video produced (on-line version installed; German, Swedish and Portuguese hardcopy versions issued to partners) | Producer | 1st August | |
| Budget revision | Partners to identify and submit to MC. travel/ subsistence under spend, additional technical costs, estimated future costs. Additionally partners to submit budget redistributions due to project direction changes | All partners | 14th May |
| Revised draft budget produced by Careers Europe, circulated and agreed by partners | MC , Careers Europe | 21st May | |
| Contract amendment form submitted to Ecotec | CXL, Careers Europe | 30th June | |
| Dissemination | All parties to fulfil dissemination activities (see dissemination plans and appendix 2 below) | All partners | |
| Post Pilot | CXL to ensure Source Creative installs all missing sections from partner websites | RH, CXL | |
| Questions having little or no value to be removed from tool. | RH, CXL | ||
| Technical Report issued by CXL. Partners feedback on revisions to themes, if necessary. | RH, CXL, all partners | 30th June | |
| Final version of Interim Evaluation Report issued | JH, iCeGS | 17th May | |
| Careers Europe to create a dissemination plan from received partner information | MC, Careers Europe | ||
| Careers Europe to improve the CXL-EU project website as a matter of priority, including the use of leaflets, photo’s, short reports, organisational logo’s, screenshots from video, complete video. Partners to send MC information to assist this process by 17th May. | MC, Careers Europe, all partners | 17th May, for info. to MC | |
| Draft of Distribution Agreement to be circulated to partners | JC, CXL | Asap | |
| Ecotec review disseminated to partners | JC, CXL | June | |
| Partners updated on date when partners will have firm information from CXl on selling the tool including any associated costs | JC, CXL | 21st June |